A. The agent to check with initial supplier.

A.1 Initial Supplier has no alternative item.
– Check if the customer can wait for the lead time.
– If yes, inform the supplier accordingly
– After sourcing, proceed to B.
A.2 Initial supplier offers an alternative item, proceed to B.

B. The agent to inform CS (Customer Success)

Email example:

Hi CS Team,

We are pleased to update regarding the following item below:

Item: Makita DTW190RFE Cordless Impact Wrench Including Tools + Charger + Batteries
Issue: Item is OOS and LT is 8 - 15 working weeks, here's the alternative item that can be offered to our customer. The price for the alternative item is higher. Below is the link FYR. 

https://eezee.sg/product/makita-td111dsae-5de898d6a4


Thank you!
B.1 If the Customer accepts the lead time

Inform Supplier accordingly.

B.2 If Customer accepts the alternative item.
– Ask CS (Customer Success) to raise a new SO (Sales Order) with the alternative item.
– Cancel old PO (Purchase Order) and then old SO (Sales Order).
– Process new SO (Sales Order) accordingly.
B.3 If the customer decides to cancel the order
a. Marketplace

– Cancel the old PO (Purchase Order) and then old SO (Sales Order).
– Proceed refund.

b. Enterprise

– Cancel the old PO (Purchase Order) and then old SO (Sales Order).

B.4 If the customer doesn’t want to accept the alternative & doesn’t want to cancel the order.

– Extend sourcing
– Seek BD’s assistance to negotiate with customers.